Earned Value Management in Project Management: EVM Formulas

Lucija Bakić

Last updated Nov 17, 2026

Your project spend can look on track while the work behind it falls weeks behind. Earned value management (EVM) is a method that compares completed work with the plan and with its cost.

This article shows what earned value is, how to calculate it, and every EVM formula on one website project. You’ll also learn how to read the results, plus EVM’s benefits, limits, setup, suitable industries, and data sources.

Key Takeaways

  • Earned value management (EVM) is a method that compares completed work with the plan and with its cost: Earned value itself is the budgeted cost of the work you’ve finished.
  • The EVM formulas build on planned value, earned value, and actual cost: Variances, indexes, and forecasts all come from comparing those three numbers.
  • EVM falls short when progress is guessed, or the baseline goes stale: An inflated percent complete or an outdated budget makes every index look more precise than it is.
  • Earned value data comes from your budget, schedule, timesheets, and progress records: Software that holds the budget and cost data saves you from rebuilding those inputs by hand.

What Is Earned Value in Project Management?

Earned value in project management is the budgeted cost of the work you’ve finished by a given date. It’s the core number in earned value management (EVM).

Earned value management (EVM) is a method that compares completed work with the plan and with its cost. PMI’s earned value standard page describes it as a methodology “for integrating scope, schedule, and resources”. In short, earned value is the number, and EVM is the method that uses it.

How Do You Calculate Earned Value (EV)?

You calculate earned value by multiplying the percent complete by the budget at completion (BAC). The earned value formula is:

Earned value = percent complete × BAC

BAC is the total budget for the work. Use your internal cost budget, not the client’s fee, because actual cost is measured at cost rates. With the fee as BAC, CPI mixes your margin into the result.

Our illustrative example is a fixed-fee website redesign with a planned cost of $60,000 over 20 weeks. Here’s how to calculate earned value at week 10, when the team has finished 40% of the work:

Earned value = 0.40 × $60,000 = $24,000

The hard part is percent complete, so give each piece of work a measurement rule. The US Government Accountability Office’s cost estimating and assessment guide describes methods that include these:

  • 0/100: The work earns its value only when it’s finished. GAO advises it only for work that starts and ends within one reporting period.
  • 50/50: Half the value is earned when the work starts and half when it ends. GAO describes it for small work within two reporting periods.
  • Weighted milestones: Each milestone earns a set share of the budget. GAO suggests it for longer work with clear interim results.
  • Percent complete: Someone estimates progress. GAO says the estimate should rest on objective, measurable completion.

For example, the website’s design phase has a $12,000 budget. Wireframes are worth 40% and mockups 60%. Wireframes are approved, so the phase has earned 40% × $12,000 = $4,800.

With earned value set, the other formulas compare it with the plan and the cost.

What Are the Earned Value Management Formulas?

The earned value management formulas are Planned Value (PV), Actual Cost (AC), Cost Variance (CV), Schedule Variance (SV), Cost Performance Index (CPI), Schedule Performance Index (SPI), and the Forecast Formulas (EAC, ETC, VAC, TCPI). The US Department of Energy’s EVMS gold card lists each one, with a different TCPI version. We’ll take a closer look at each.

Planned Value (PV)

Planned value is the budgeted cost of the work scheduled by a given date. You multiply the share of work the plan expects by BAC:

PV = planned percent complete × BAC

The website plan expected 50% of the work done by week 10. So PV = 0.50 × $60,000 = $30,000.

Actual Cost (AC)

Actual cost is what all the work done so far really cost, including work in progress. It’s logged hours at each person’s cost rate, plus expenses. Cost the hours the same way you costed the budget. If the budget includes overhead, AC must include it too, or CPI looks better than it is. In the example, AC at week 10 is $21,000.

Productive doesn’t calculate earned value or the other formulas. On its Ultimate plan, the overhead calculator adds a share of overhead to the cost of each tracked hour.

You add facility and internal costs on top of each person’s cost rate, so your overall costs cover running costs too.

A screenshot of Productive’s overhead cost settings adding facility costs to each hour.


Add facility and internal costs to each hour’s cost with Productive’s Overhead Calculator.

I generated all the financial reports for our agency, and no other software out there was able to calculate the overheads and spread them across all our clients. That was so important for us because other tools would show it as profit, and we would have to manually spread them across our clients.

Chris Stones,
Strategic and Operations Director, Mitchell & Stones

Cost Variance (CV)

Cost variance is earned value minus actual cost, the money you’re over or under for the work done:

CV = EV – AC

In the example, CV = $24,000 – $21,000 = $3,000. A positive number means the work done cost less than its budgeted value. Here’s more on how to analyze cost variance in detail.

Schedule Variance (SV)

Schedule variance is earned value minus planned value, measured in money, not days:

SV = EV – PV

Here, SV = $24,000 – $30,000 = -$6,000, so $6,000 of planned work isn’t done yet. A negative SV means you’re behind the plan.

Cost Performance Index (CPI)

The cost performance index is earned value divided by actual cost:

CPI = EV ÷ AC

In the example, CPI = $24,000 ÷ $21,000 = 1.14. Each dollar spent has produced about $1.14 of budgeted work. Above 1.0 is favorable, and below 1.0 is unfavorable.

Schedule Performance Index (SPI)

The schedule performance index is earned value divided by planned value:

SPI = EV ÷ PV

Here, SPI = $24,000 ÷ $30,000 = 0.80: the team has done 80% of the work planned by now. An SPI of 1.0 means you’re on plan. Learn how to track schedule performance over time.

Forecast Formulas (EAC, ETC, VAC, TCPI)

The forecast formulas project the final cost if current trends hold, plus the efficiency needed to stay on budget. Each one answers one question:

  • Estimate at completion (EAC) = BAC ÷ CPI: What will the project cost in total? $60,000 ÷ 1.143 = about $52,500.
  • Estimate to complete (ETC) = EAC – AC: How much more will you spend? $52,500 – $21,000 = $31,500.
  • Variance at completion (VAC) = BAC – EAC: Will you finish over or under budget? $60,000 – $52,500 = $7,500 under.
  • To-complete performance index (TCPI) = (BAC – EV) ÷ (BAC – AC): How efficient must the rest of the work be to hit BAC? $36,000 ÷ $39,000 = 0.92.

EAC, ETC, and VAC assume today’s cost efficiency continues. Our guide to estimate at completion shows other ways to forecast the final cost. With the numbers in hand, the next job is reading them together.

How Do You Read Earned Value Analysis Results?

You read earned value analysis results by comparing cost and schedule together, then checking what the forecasts assume. The website project’s results at week 10 read like this:

FormulaResultWhat it says
EV$24,00040% of the planned cost of work is done
PV$30,000The plan expected 50% by now
AC$21,000What all the work so far has cost
CV$3,000The work done cost less than its budgeted value
SV-$6,000$6,000 of planned work is late
CPI1.14Each dollar bought about $1.14 of budgeted work
SPI0.80The team has done 80% of the work planned by now
EAC$52,500Projected final cost if CPI holds
ETC$31,500Projected cost of the remaining work
VAC$7,500Projected saving against BAC if CPI holds
TCPI0.92Cost efficiency needed to finish within BAC

Read together, the example says the team is cost-efficient but behind plan. The work done cost less than budgeted, but less work is done than planned. If catching up means overtime or senior staff, that saving can disappear.

If CPI drops below 1.0, check for unapproved scope, pricier people, or low estimates before you re-plan. These checks are our suggestion.

Productive AI lets you ask for a report in plain language, like last month’s hours by person. The AI Assistant returns a link to that report with filters applied, so you don’t set them by hand.

A screenshot of Productive’s AI Assistant flagging projects at financial risk.


Ask the AI Assistant for insights in plain language with Productive.

Find out where your team’s hours went.

Read this way, the numbers give EVM its benefits.

What Are the Benefits of Earned Value Project Management?

The benefits of earned value project management are one measure, early forecasts, a recovery target, and better estimates. The grouping is ours:

  • One measure for cost and schedule: CV and SV both start from earned value, so both judge the same finished work.
  • Early forecasts: EAC gives a projected final cost while there’s still budget left to act on.
  • A recovery target: TCPI tells you the cost efficiency the remaining work needs to finish within BAC.
  • Better estimates next time: Recording CPI by phase on finished projects gives you a base for pricing similar work.

For agencies, cost and schedule problems are both common. PMI’s 2025 survey of 130 US agency staff covered major campaign challenges in the past year. Going over budget was one for 55% of respondents, and overdue deadlines for 54%.

Those benefits hold only when the inputs are honest, which is where EVM falls short.

Where Does Earned Value Management Fall Short?

Earned value management falls short when progress is guessed, hours stand in for progress, or the baseline goes stale. It also misses quality and sequence. The list is our own:

  • Guessed percent complete: An optimistic 70% raises EV, so CPI and SPI look better than the work is.
  • Hours logged as progress: A team can spend half its hours and finish a third of the work. If percent complete is hours spent divided by hours budgeted, EV rises with spending. CPI then compares only planned and actual cost rates.
  • A stale baseline: If approved scope changes don’t reach BAC, every index compares today’s work with an old plan.
  • SPI drifting to 1.0: At completion, EV and PV both equal BAC. So SPI ends at 1.0 even on a late project.
  • Quality and sequence: EV credits work as done even if it later needs rework. One index can also hide a late task that blocks others.

The setup is where you deal with the first three.

How Do You Set Up Earned Value Management?

You set up earned value management by defining, budgeting, and scheduling work packages, then measuring them by set rules. The four parts are our recommendation. Each one produces an input for the formulas:

  • Work packages: Use your phases or deliverables. For a website, these might be discovery, design, development, and launch.
  • Budgets and dates: The package budgets, at cost, add up to BAC. Spread them across the dates, and you get PV for any week.
  • Measurement rules: Pick one per package before it starts. Short tasks can use 0/100, and long ones weighted milestones.
  • A fixed cadence: Run the earned value calculation monthly or at each milestone. Change the baseline, BAC, and PV only for approved changes.

The setup fits some kinds of work better than others.

Which Industries Is EVM Suitable For?

EVM is suitable for industries whose projects have a defined scope and a baseline plan before work starts. Construction and engineering projects fit once drawings and quantities are agreed.

For agencies and consultancies, EVM project management fits fixed-fee projects with agreed deliverables. Open-ended retainers and agile work fit less well, because scope can change each period, so BAC keeps resetting. Whatever the industry, EVM needs current data from four places.

Where Does Earned Value Data Come From?

Earned value data comes from your budget, your schedule, timesheets with cost rates, and progress records. Each input maps to one of them:

InputWhere it comes from
Budget at completion (BAC)The approved cost budget for each phase or service
Planned value (PV)That budget spread across the schedule’s dates
Earned value (EV)Percent complete from milestones or finished deliverables, times the budget
Actual cost (AC)Logged hours at cost rates (with overhead, if budgeted), plus expenses

A spreadsheet works for one project. Across several, someone exports timesheets, applies cost rates, and pastes totals into each budget sheet every period. Between updates, a budget kept in Excel shows old costs, and AC goes stale.

Dedicated earned value management software (EVM software) calculates CPI and SPI for you. A project or PSA tool can hold the budget and cost inputs in one place instead.

Productive doesn’t calculate earned value, CPI, or SPI. It holds budget totals and estimated costs, expenses, scheduled bookings, and hours costed as they’re logged. You can see where your team’s time is going on each budget. Percent complete and the formulas are up to you.

A screenshot of Productive’s company timesheet with each person’s logged hours per day.


Track your team’s time on a budget in Productive.

If you’re comparing tools, see our list of project cost management software.

Track Budgets, Time, and Costs in One Place

Earned value management turns planned value, earned value, and actual cost into one check on cost and schedule. It works when progress follows a set rule, BAC uses cost, and only approved changes move the baseline.

Those inputs are easier to keep current when budgets, logged hours, and bookings are in one tool. Productive is an agentic PSA platform where you run projects, budgets, and resources in one place.

Book a demo with Productive to see the budget, cost, and scheduled work for each project.

Track Costs Against Each Budget as Work Happens

Logged hours and expenses roll up against each budget automatically in Productive, so costs stay current.

Book a demo

Lucija Bakić

Product Marketing Specialist