Cost Performance Index in Project Management: CPI Definition & Formula
Your cost performance index in project management tells you whether your budget is at risk or right on track.
It helps project managers take corrective actions to ensure successful project outcomes, making it one of the core project management metrics. However, calculating it can be confusing if you don’t understand some key terminology.
This article will discuss the core performance index formula, what the values mean, and why it’s so important to maintaining optimal financial performance.
What Is the Cost Performance Index in Project Management?
The cost performance index compares your planned costs to actual expenses, with values indicating whether you’re on budget (1.0), over budget (less than 1.0), or under budget (greater than 1.0).
It’s part of earned value (EV) analysis, which also includes metrics such as cost variance and schedule variance.
The cost performance index and cost variance are related concepts, but their business focus is different. The cost variance formula depicts the specific amount of budget that has been either saved or exceeded, while the cost performance index reflects the overall efficiency of your financial management.
How to Calculate CPI? Cost Performance Index Formula
The basic cost performance index formula is:
projected cost (earned value) / actual cost = CPI
To calculate your earned value during a particular point in the project schedule, multiply the completion percentage with your original budget.
Your actual cost is the amount of money during the analyzed time period.
To provide a practical example:
Let’s say the original budget of a construction project is $100,000. If the project is 50% complete, the earned value equals 0.5 x $100,000 = $50,000.
If your actual cost is $40,000, the CPI would look like this:
$50,000 (earned value) / $40,000 (actual cost) = 1.25 (CPI)
This means your project budget is operating at 125% project efficiency, putting you ahead of your costs.
Instead of tracking your performance indicators manually, you can control costs with a project management software like Productive.
Productive enables you to build and manage budgets of all types, monitor actual progress, and forecast budget burn and profit margins — learn more about optimizing costs with Productive.
The Cost Performance Index Operating Range
Speaking generically, this is what your CPI index ranges mean:
- Index of 1.0: An index that’s around the 1.0 value signals that the project activities are progressing according to plan. A small overflow (for example, an index of 1.1) is usually also acceptable, as some projects will be liable to scope creep despite how comprehensive your project plan is.
- Index under 1.0: An index that exceeds 1.0 means that you’re working with a budget overrun. Depending on how your projects are set up, some amount of overrun can be acceptable, but at a certain point, it’ll start affecting business profitability. This usually signals workflow issues, capacity planning gaps, or other process delays.
- Index over 1.0: An index over 1.0 means that you’re ahead of your budget. While this is usually seen as a positive, there’s such a thing as having too much of a good thing. Saving up an unexpected amount of your budget can signal issues. For example, maybe there are overlooked milestones, or the quality of the deliverables is lower than average.
CPI Examples & Targets
Since every business has its specificities and particular context, your CPI benchmarks will largely depend on historical performance. You’ll want to start gathering data as soon as possible to make informed decisions.
You can monitor CPI across various periods to establish which CPI is acceptable and still results in project success and which signals project risk that needs to be addressed as soon as possible.
For example, a cost performance index research that examined the cost library of the US Air Force discovered that once projects have a low CPI and are past a certain completion percentage, it’s unlikely that they’ll recover:
Despite any optimistic claims of the contractor, it is extremely unlikely that a contractor will recover from a cumulative cost overrun after the contract is 50 percent complete, especially if the TCPI exceeds the CPI by more than 10 percent. In fact, results of the sensitivity analysis show that the CPI range is stable as early as the 20 percent complete point.
Source: Cost Performance Index Stability: Fact or Fiction?
As you can see, this data is highly contextual. Ideally, a project manager would set target CPI rates with the project team before the execution to help support cost efficiency and project performance.
The Importance of CPI Analysis for Project Performance
Research conducted by McKinsey on IT projects with cost overrun has identified a couple of common risk factors during the project management process:
- Unclear objectives and lack of business focus (13%)
- Unrealistic schedule and reactive planning (11%)
- Shifting requirements and technical complexity (9%)
- Unaligned team and lack of skills (6%)
Although most projects can withstand the downsides of schedule and cost overrun, 17% of IT projects perform so poorly that they threaten the continued functioning of the business.
The cost performance index (CPI) helps project managers control these risks by identifying potential financial issues early in the project lifecycle. By setting CPI targets, tracking costs, and comparing them to internal and external industry benchmarks, project management professionals can get more reliable insights into their project status for proactive decision-making.
This also helps improve project quality and outcomes for future projects by developing a set of standards to adhere to. Continuous monitoring and cost control also help set more accurate budget estimates in the future, helping combat unrealistic schedules.
Optimizing Your Cost Performance With Productive
Productive is an all-in-one agency management software with a range of features for resource planning, project management, budget management, and comprehensive analytics.
To ensure your project is on track and manage progress, you can use the integrated Time Tracking feature to track and approve billable hours. You can also organize simple or complex projects with a variety of project views, including Gantt, Kanban, Workload, Calendar, and more.
Productive’s Budgeting tools help you control your budget burn, manage overhead and expenses, invoice and track payments, and get consolidated data on key metrics.
A great example is Productive’s Budgeting and Profitability charts, which provide real-time insights into pivotal metrics for project and business success.
Your budget burn will be updated automatically based on your billable hours tracked and billable rates. Then, by switching to the Profitability view, you can see how your project progress impacts your revenue and profit margins.
You can also turn on forecast charts to visualize your project planning and finances for upcoming periods of time, based on your employee scheduling in the Resource Planning module.
Productive also includes overhead and expense management to provide project managers with a deep understanding of the project in terms of cost and success.
Additional features include:
- Reports templates library with 50+ agency-focused reports
- Invoice creation and tracking (integrations include Xero and QuickBooks)
- Employee scheduling, availability management, and utilization insights
- Task management, collaboration, and custom workflow automations
- A Client Portal for insights into progress and budgets (with custom permissions)
Book a demo with Productive today to find out what it can do for your business.
Optimize Your Cost Performance With Productive
Switch from multiple tools and spreadsheets to an all-in-one solution for project and financial management.
FAQ
1. How does the cost performance index (CPI) influence project forecasting and decision-making?
CPI supports project forecasting and provides project management teams with the necessary information to make data-driven project management decisions. By analyzing CPI, project managers can monitor project costs during project execution to identify potential risks and make timely interventions. By estimating the total cost at project completion (estimate at completion or EAC), businesses can analyze their processes, make long-term improvements, and make better estimates for future projects (including resources, timelines, and project scope).
2. What are the common pitfalls when calculating and analyzing the cost performance index (CPI)?
Common pitfalls of monitoring your CPI are not considering its context properly, for example, the phase of the project and your previous internal benchmarks. Another potential issue is monitoring CPI in isolation, i.e. without calculating other performance metrics such as schedule or cost variance.
3. How can CPI be used with other earned value management (EVM) metrics to improve project management?
CPI is often used alongside other EVM metrics, such as the schedule performance index, to provide a more comprehensive view of project performance. While CPI focuses on cost efficiency, SPI tracks schedule efficiency. Together, they can highlight whether a project is both on budget and on time, enabling more holistic project management.
4. Can the cost performance index (CPI) be applied to projects of all sizes and industries?
CPI is a versatile metric that can be applied across various industries and project sizes. It’s frequently used in the context of the construction industry, but is also valuable for the professional services realm of project management. Keep in mind that CPI benchmarks and target values can differ from industry to industry and even project to project.